Lisbon Metro Misses Elevator Target, Pushes Four Stations to 2028

Metro de Lisboa aimed for 93% of stations with elevators in 2025 and now expects 86% by the end of 2026. Which stations are delayed and what comes next.

Explore the sleek, modern architecture of an empty Vienna subway station interior.
Photo: Travel Photographer / Pexels

Metro de Lisboa (Lisbon’s underground railway operator) has missed its goal of giving 93% of its stations full step-free access in 2025 and now expects to reach 86% by the end of this year, the company told the news agency Lusa, as reported by Observador. Elevator work at four more stations has slipped from 2027 to 2028.

For wheelchair users, parents with strollers and anyone who cannot manage stairs, the delay means several stations on the network will stay out of reach for longer than planned. The Metro blamed technical, operational and administrative obstacles that held up the planned works.

How many Lisbon Metro stations have elevators

The company’s website lists 47 stations with elevators out of a total of 56. The Metro’s measure of “full accessibility” only counts whether elevators exist in a station. It does not mean they are working on a given day.

The gap goes back a long way. The national accessibility plan (Plano Nacional para a Promoção da Acessibilidade, or PNPA), approved by the government in 2007, told the Metro to finish adapting its stations so the whole network would be usable by people with special needs. At that time the network had 41 stations, 25 of them without elevators or escalators. The plan turns 20 years old soon, and the work is still not complete.

Which stations are delayed

Last year the Metro set out to install elevators in 10 stations. Five of them, Campo Pequeno, Intendente, Picoas, Martim Moniz and Praça de Espanha, were due by the end of 2025. Martim Moniz and Praça de Espanha ran late and were only finished this summer. Workers found a block of concrete of about 12 square meters at Martim Moniz, and a telecommunications room had to be moved at Praça de Espanha, according to the company.

The other five stations, Alto dos Moinhos, Anjos, Avenida, Jardim Zoológico and Laranjeiras, were meant to have elevators by 2027. The Metro now says four of them will wait until 2028. Avenida keeps its 2027 date: after the design was revised, the company plans to open a public tender by the end of 2026.

For the remaining four, the Metro asked Lisbon City Council (Câmara Municipal de Lisboa) for its prior opinion in March 2026. Only two of those requests were answered in October. The other two are still pending.

Parque, Pontinha and Baixa-Chiado

Parque, one of the deepest stations on the network, will not get elevators at all for now. It has only fixed stairs and escalators, and the company says the conditions above and below ground have so far ruled out a workable design. A technical feasibility study is under way, and its findings will go to the city council.

At Pontinha, both existing elevators need to be fully replaced. The Metro says a project for the building work and new equipment should be in place by summer 2027, and it apologized for the disruption.

At Baixa-Chiado, the lift platform that connects the station to street level on Rua do Crucifixo is out of order. The Metro says the equipment is old and specialist repair support is hard to find, and it is asking suppliers for a more reliable replacement.

What it means for passengers

A station counted as accessible may still have a broken lift, since the Metro’s own figure only tracks whether one is installed. Stations still without elevators, plus Parque with no plan in place, will remain hard or impossible to use without stairs for years.

This year the Metro started a new maintenance contract with Kone Portugal at Baixa-Chiado and Aeroporto, with technicians stationed at both stations at all times. The pilot covers 22 escalators and six elevators. The company says elevator availability at both stations has been 100% with no breakdowns since it began, escalators at Aeroporto reached 100% and those at Baixa-Chiado just under 100%. No complaints about equipment faults have been recorded there.

The Metro said financial, technical and operational limits slowed accessibility work over the past two decades, especially the financial crisis of 2011. It acknowledged that the lack of step-free access limits the independence and mobility of many passengers and said the investments are a strategic priority.

Source: Observador